50 kW / 110 kWh Farm Solar Storage with Zero-Export Control in Cyprus
YOTAI PARTNER REFERENCE · YINTU ENERGY SOLUTIONS
The Larnaca farm reference in YOTAI's collection combines PV, a 50 kW / 110 kWh storage unit and the utility connection. Its principal control requirement is zero export, alongside greater use of locally generated solar and a lower grid-import requirement during selected operating periods.
Project at a Glance
| Location | Larnaca, Cyprus |
|---|---|
| Application | Farm solar-storage system |
| Project scale in source | 50 kW / 110 kWh |
| Equipment in source | One Smart 110 kWh PV-storage all-in-one unit |
| Grid-exchange requirement | Zero-export target |
Customer Situation and Energy Requirements
A farm with PV can have excess generation at one time and a need to import energy later. When the connection requires zero export, surplus generation also needs an approved destination or output-reduction response. Battery storage provides useful flexibility within its charging and energy limits.
The customer objectives include lower electricity expenditure and delaying transformer or line expansion where feasible. The presentation supplies these objectives without load measurements or an engineering assessment of the existing connection.
Storage Integration and Control Strategy
The source describes a PV-storage-grid architecture serving farm loads. Its operating priority is to avoid grid import when PV and available battery discharge can supply the load, while maintaining the zero-export requirement. These two directions of power flow need coordinated site measurements.
A battery can absorb selected solar surplus while sufficient charging headroom remains. When it reaches its SOC or charging-power limit, the project needs a defined way to manage remaining generation, such as compatible PV output control. Meter location, communications and fail-safe behavior form part of that design.
Zero export is an operating target at the agreed measurement point. A new project should specify the required control performance, margins and protection for sudden load changes rather than assume that a software setpoint alone establishes compliance under every transient condition.
Intended Operational Value
The intended value is to use more solar energy locally and support a defined portion of farm demand with stored energy. A well-specified control strategy can align storage operation with the connection restriction and the farm's working schedule.
The reference includes no measured self-consumption percentage, annual savings or confirmed avoided-upgrade cost. Those results depend on the real generation profile, demand pattern, usable energy and connection conditions.
Planning a Comparable Installation
- Record load and solar generation across the relevant agricultural season.
- Confirm the utility measurement point and the zero-export requirements.
- Define battery reserve and the sequence used when storage is full.
- Check peak duration before considering any connection-upgrade deferral.
Related YINTU Storage Options
For a new farm assessment, review the 50 kW / 150.5 kWh hybrid storage system and confirm that its proposed grid interface and export controls match the project. It is a different catalogue configuration from the case's 110 kWh unit. Our commercial storage budget guide covers control and electrical-interface costs that should accompany equipment selection.
How YINTU Supports a Comparable Project
YINTU is an energy storage solution provider working with manufacturing partners, including YOTAI. We support application assessment, equipment selection and technical coordination for customer-specific projects. This article presents a supplier reference. YINTU does not claim to have designed or installed the featured site.
For a new proposal, share farm demand, PV production, the connection agreement and any required reserve for essential services. The agreed technical scope defines equipment, interfaces and service responsibilities. The source's 110 kWh equipment family should not be treated as identical to a current catalogue product with a different rating.
Project Questions
Does zero export mean the farm operates off-grid?
Zero export describes power exchange while connected to the utility. The supplied architecture includes the grid and does not establish an off-grid installation.
Will more battery kWh alone guarantee zero export?
Energy capacity is only one input. Charging power, available SOC, measurements and control of generation also determine the response.
Project facts and photograph: YOTAI overseas C&I case collection, September 2026, slide 7. The source describes the configuration, requirements and technical challenges. Application analysis is provided by YINTU. The collection does not supply metered performance results for this project.