How Solar and Battery Dispatch Can Lower a Factory’s Electricity Bill
YINTU ENERGY STORAGE KNOWLEDGE
A rooftop solar system and battery lower a factory’s electricity bill through the timing of grid imports. A useful feasibility study compares the same factory with PV alone and with PV plus storage. That comparison shows how much value the battery adds and whether it comes from fewer purchased kilowatt-hours, lower billed demand, or both.
Rebuild the bill from interval data before selecting the battery
Collect site-meter data for a full year where practicable, ideally at the utility's demand interval, plus the current tariff, PV generation and export terms. Note demand ratchets, seasonal rates and billing-period definitions where they apply. Reproduce a typical invoice from the raw data before testing dispatch. A load profile with a short evening peak will produce a different design from one with four hours of overlapping production shifts.
Model solar charging at its opportunity cost
Suppose you store 100 kWh of midday PV that could otherwise be sold at 0.04 per kWh and recover 88 kWh at the meter later, using an illustrative 88% AC-to-AC efficiency. At a later import tariff of 0.20 per kWh, you avoid 17.60 in purchases and give up 4.00 in export revenue. The gross gain is 13.60 in the same currency before battery wear and any costs outside the measurement boundary. Use actual seasonal rates and losses, and check whether export had any value in the first place.
Treat demand savings as a separate simulation
Suppose the billed peak would have been 450 kW and a dispatch plan caps it at 400 kW throughout the relevant demand intervals. At 12 per kW per month, the illustrative reduction is 600 for that billing period, subject to the tariff and any ratchet. A missed higher peak can erase the expected savings. Simulate the rest of the month, including whether charging creates a new peak and whether the battery is available at the next event.
Plan charging, reserve and export control together
A factory cannot use the same energy simultaneously for evening arbitrage and emergency reserve. Prioritize required export limits and equipment protections, then model how enough battery headroom can remain for midday surplus and enough SOC for later demand or backup. If a retrofit keeps the existing PV inverter, verify the point-of-connection meter, curtailment method, and interfaces.
Compare a retrofit with a new hybrid installation
YINTU helps integrators evaluate commercial configurations against interval data and the site connection. See the 125 kW / 261 kWh commercial PV retrofit application and our guide to export control, demand management and time shifting for different control objectives.